Changing schedule for weather or other immediate events
If CPRIII 6.9 is being used with a working pager system, and the time switches have
CP22 chips, the following procedure will allow you to change a schedule immediately.
Notice in the calendar (Fig. 20), the Kennedy Jr High schedule for February 10 – 11 is
normal. There is not a holiday plan there.
Fig. 20
Say, for instance, you have a situation where you need to turn the flashers off for
February 10
– 11. Perhaps a snowstorm, or other unplanned event, requires immediate
attention. The first thing to do is click the Holiday Plan in available Day Plans. Then
click on February 10
th
and 11
th
. (Fig. 21)
Fig. 21